Progress Photos

December 2017 - Western Perimeter Fence Line Relocation

December 2017 - Western Perimeter Fence Line Relocation

December 2017 - Final Restoration South of 115 River Road

December 2017 - Final Restoration South of 115 River Road

December 2017 - Stockpile Management and Crushing Operations

December 2017 - Stockpile Management and Crushing Operations

December 2017 - Clearing and ISS on the Main Quanta Site

December 2017 - Clearing and ISS on the Main Quanta Site

December 2017 - South Parking Lot Clean-Up

December 2017 - South Parking Lot Clean-Up

December 2017 - Transporting Pilings from Clearing on Main Quanta Site

December 2017 - Transporting Pilings from Clearing on Main Quanta Site

December 2017 - Clearing and Foaming on the Main Quanta Site

December 2017 - Clearing and Foaming on the Main Quanta Site

December 2017 - iPark Paving

December 2017 - iPark Paving

December 2017 - Crushing Operations (with foam)

December 2017 - Crushing Operations (with foam)

December 2017 - Pier Building Water Line Installation

December 2017 - Pier Building Water Line Installation

November 2017 - Restoration South of 115 River Road

November 2017 - Restoration South of 115 River Road

November 2017 - Pier Building Water Line Installation

November 2017 - Pier Building Water Line Installation

November 2017 - Paving South of 115 River Road

November 2017 - Paving South of 115 River Road

November 2017 - Pier Building Water Line Installation

November 2017 - Pier Building Water Line Installation

November 2017 - Pre-Clearing on the Main Quanta Site

November 2017 - Pre-Clearing on the Main Quanta Site

November 2017 - ISS on the Main Quanta Site

November 2017 - ISS on the Main Quanta Site

November 2017 - Posi-Shell Application

November 2017 - Posi-Shell Application

November 2017 - Backfilling Activities

November 2017 - Backfilling Activities

October 2017 - ISS and Pre-Clearing

October 2017 - ISS and Pre-Clearing

October 2017 - Restoration and Concrete Removal

October 2017 - Restoration and Concrete Removal

October 2017 - Misting System

October 2017 - Misting System

October 2017 - Crane Staging Location

October 2017 - Crane Staging Location

October 2017 - Wharf Removal

October 2017 - Wharf Removal

October 2017 - Clearing Work

October 2017 - Clearing Work

October 2017 - ISS and Posi-Shell Application

October 2017 - ISS and Posi-Shell Application

October 2017 - Restoration

October 2017 - Restoration

September 2017 - PSE&G gas line work

September 2017 - PSE&G gas line work

September 2017 - Non-toxic foam applied to exposed soil to help control odors

September 2017 - Non-toxic foam applied to exposed soil to help control odors

September 2017 - Re-grading after completion of ISS

September 2017 - Re-grading after completion of ISS

September 2017 - Applying a durable, weather-proof, hard shell covering (posi-shell) to exposed soil to help control odors

September 2017 - Applying a durable, weather-proof, hard shell covering (posi-shell) to exposed soil to help control odors

September 2017 - Removing underground debris

September 2017 - Removing underground debris

September 2017 - Installation of a “clean road” (for construction vehicles that do not contact areas of contamination)

September 2017 - Installation of a “clean road” (for construction vehicles that do not contact areas of contamination)

September 2017 - Stockpile management

September 2017 - Stockpile management

August 2017 - Removing concrete

August 2017 - Removing concrete

August 2017 - Installation of steel sheetpile bulkhead outboard of main Quanta property

August 2017 - Installation of steel sheetpile bulkhead outboard of main Quanta property

August 2017 - Completion of walkway on the south side of 115 River Road for visitors to the Pier 115 restaurant

August 2017 - Completion of walkway on the south side of 115 River Road for visitors to the Pier 115 restaurant

July 2017 - Preparation of Block 93 for remediation

July 2017 - Preparation of Block 93 for remediation

July 2017 - ISS of soils on Block 93

July 2017 - ISS of soils on Block 93

July 2017 - Preparation of area south of 115 River Road Building for remediation

July 2017 - Preparation of area south of 115 River Road Building for remediation

July 2017 - Showing progress of the shoreline bulkhead installation

July 2017 - Showing progress of the shoreline bulkhead installation

July 2017 - Bracing installed on west wall of pier 115

July 2017 - Bracing installed on west wall of pier 115

July 2017 - Repairs and striping of parking lot on north side of 115 River Road building

July 2017 - Repairs and striping of parking lot on north side of 115 River Road building

July 2017 - Relocation of the batch plant to the east side of River Road

July 2017 - Relocation of the batch plant to the east side of River Road

July 2017 - Completion of access road from north to south of 115 River Road for parking

July 2017 - Completion of access road from north to south of 115 River Road for parking

July 2017 - Looking at excavators and batch plant on main Quanta property

July 2017 - Looking at excavators and batch plant on main Quanta property

July 2017 - Applying foam for odor suppression on the main Quanta

July 2017 - Applying foam for odor suppression on the main Quanta

July 2017 - Stockpile of soil

July 2017 - Stockpile of soil

July 2017 - ISS mixing activities on the main Quanta property

July 2017 - ISS mixing activities on the main Quanta property

July 2017 - Opening of access road from north to south of 115 River Road building

July 2017 - Opening of access road from north to south of 115 River Road building

July 2017 - Management of concrete on the main Quanta property

July 2017 - Management of concrete on the main Quanta property

July 2017 - Restoring portions of Block 93

July 2017 - Restoring portions of Block 93

July 2017 - Cutting off sheet piles to appropriate elevation outboard of main Quanta property

July 2017 - Cutting off sheet piles to appropriate elevation outboard of main Quanta property

July 2017 - Installation of steel sheetpile bulkhead outboard of main Quanta property

July 2017 - Installation of steel sheetpile bulkhead outboard of main Quanta property

July 2017 - ISS activities on the main Quanta property

July 2017 - ISS activities on the main Quanta property

July 2017 - Applying foam to remediation activities for odor suppression on main Quanta property

July 2017 - Applying foam to remediation activities for odor suppression on main Quanta property

July 2017 - Preparing area south of 115 River Road for remediation activities

July 2017 - Preparing area south of 115 River Road for remediation activities

July 2017 - Progress of steel sheetpile bulkhead

July 2017 - Progress of steel sheetpile bulkhead

June 2017 - Water quality controls during bulkhead work

June 2017 - Water quality controls during bulkhead work

June 2017 - Clearing vegetation east of River Road in preparation for ISS

June 2017 - Clearing vegetation east of River Road in preparation for ISS

June 2017 - Installing steel bulkhead to protect the river north of the 115 River Road pier

June 2017 - Installing steel bulkhead to protect the river north of the 115 River Road pier

June 2017 - Using a bucket auger to mix concrete and contaminated soils (ISS) west of River Road. Collecting ISS sample

June 2017 - Using a bucket auger to mix concrete and contaminated soils (ISS) west of River Road. Collecting ISS sample

June 2017 - Spraying foam to suppress odors around ISS site west of River Road

June 2017 - Spraying foam to suppress odors around ISS site west of River Road

June 2017 - Using a bucket auger to mix cement and contaminated soil (ISS) west of River Road

June 2017 - Using a bucket auger to mix cement and contaminated soil (ISS) west of River Road

June 2017 - Completed ISS west of River Road

June 2017 - Completed ISS west of River Road

June 2017 - Mixing cement and contaminated soil (ISS) west of River Road and using foam to suppress odors

June 2017 - Mixing cement and contaminated soil (ISS) west of River Road and using foam to suppress odors

May 2017 - Constructing a temporary parking lot for the pier building

May 2017 - Constructing a temporary parking lot for the pier building

May 2017 - Covering exposed soils west of River Road with foam to suppress odors

May 2017 - Covering exposed soils west of River Road with foam to suppress odors

March 2017 - Looking southeast toward the former 115 River Road building after demolition of the first 100-feet of building

March 2017 - Looking southeast toward the former 115 River Road building after demolition of the first 100-feet of building

March 2017 - Looking southeast toward active demolition of the 115 River Road building in preparation for the OU1 Remedial Action

March 2017 - Looking southeast toward active demolition of the 115 River Road building in preparation for the OU1 Remedial Action